With the good run of dry weather in the Northern Rivers, work is progressing well with the final layer of gravel being applied on the Tweed Valley Rail Trail (Stage One of the Northern Rivers Rail Trail), with the trail still on schedule to open in early 2023.
Tweed Council Project Manager Iain Lonsdale said that Hazel Bros crews are expected to lay 300 to 400 metres per day until it is completed later this year.
Workers have removed almost all of the railway track along the 24km Tweed section of the trail with work progressing well on bridges. With painting and structural work nearing completion, the bridges will have prefabricated decking and handrails installed.
The majority of the trail will be gravel, while some sections in villages and railway stations are to be sealed in asphalt and concrete.
Excitement and interest is growing from rail trail users and people interested in operating businesses along the trail. A new logo has been released to the public and merchandise will soon be available from the Tweed Tourism Visitor Information Centre which recently moved back to the old luggage check-in room at the station after the devastating destruction of the premises in the February floods.
Note again the trail is not yet open.
Rail Trails Australia’s regional representatives are often testing out ‘their’ rail trails in the regi...
Our vice-president Steven Kaye was interviewed by Nic Healey on ABC radio (Victoria) this week. He discussed how local c...
Get ready to ride the Great Victorian Rail Trail (GVRT) on Saturday, March 29. Cycle Dindi is a fully supported, family ...
Rail Trails Australia has announced the winners of $10,000 worth of grants designed to assist community organisations to...
Time is running out on the public consultation for an extension of the Mornington Railside Trail on the Mornington Penin...
Transforming a disused railway line into a prized tourist attraction and public space is no easy task. The Summer 2024-2...
Building a shared bridge over busy Toorak Rd on the Outer Circle Rail Trail in Melbourne was not one of the state gove...
Tablelands Regional Council (TRC) and Mareeba Shire Council gathered at Walkamin recently to celebrate the joining of No...
The excitement continues in the Northern Rivers region of NSW with the official opening of Stage 3 of the Northern River...
The Barossa Council has been conducting a cleanup of the Angaston Station precinct on the Barossa Rail Trail. Invasive s...
The duplication of Adelaide’s Main South Rd to Aldinga, and its new shared path, have given users of the Coast to ...
Get ready for a fun-filled day of cycling on the scenic Great Victorian Rail Trail on Sunday, March 2, 2025. This family...
Plans for an 8km extension of the Mornington Railside Trail as part of the ambitious Peninsula Trails project in Victori...
With 92% of respondents to a survey wanting more trail, Gympie Regional Council is starting detailed design of an extens...
This year’s Great Victorian Bike Ride hit the rail trails, with Day 7 (November 29) involving a 77km stretch of th...
An iconic hotel on the 25km Dawes Range “tunnel” section of the Boyne Burnett Inland Rail Trail is making a ...
Stay up to date with the latest news about Rail Trails with our free email news.
Register for news updatesRail Trails Australia’s regional representatives are often testing out ‘their’ rail trails in the regi...
Our vice-president Steven Kaye was interviewed by Nic Healey on ABC radio (Victoria) this week. He discussed how local c...
Get ready to ride the Great Victorian Rail Trail (GVRT) on Saturday, March 29. Cycle Dindi is a fully supported, family ...
Rail Trails Australia has announced the winners of $10,000 worth of grants designed to assist community organisations to...
Time is running out on the public consultation for an extension of the Mornington Railside Trail on the Mornington Penin...
Transforming a disused railway line into a prized tourist attraction and public space is no easy task. The Summer 2024-2...
Building a shared bridge over busy Toorak Rd on the Outer Circle Rail Trail in Melbourne was not one of the state gove...
Tablelands Regional Council (TRC) and Mareeba Shire Council gathered at Walkamin recently to celebrate the joining of No...
The excitement continues in the Northern Rivers region of NSW with the official opening of Stage 3 of the Northern River...
The Barossa Council has been conducting a cleanup of the Angaston Station precinct on the Barossa Rail Trail. Invasive s...
The duplication of Adelaide’s Main South Rd to Aldinga, and its new shared path, have given users of the Coast to ...
Get ready for a fun-filled day of cycling on the scenic Great Victorian Rail Trail on Sunday, March 2, 2025. This family...
Plans for an 8km extension of the Mornington Railside Trail as part of the ambitious Peninsula Trails project in Victori...
With 92% of respondents to a survey wanting more trail, Gympie Regional Council is starting detailed design of an extens...
This year’s Great Victorian Bike Ride hit the rail trails, with Day 7 (November 29) involving a 77km stretch of th...
An iconic hotel on the 25km Dawes Range “tunnel” section of the Boyne Burnett Inland Rail Trail is making a ...
3 comments on “Tweed Northern Rivers Rail Trail Getting Closer”
Great to see this progress. We are so excited to be able to rid another trail in NSW. We have strong family ties with Murwillumbah and the Tweed so it will be great to rediscover the region.
G'day Friends 'over the border'! I am so excited for all of You wonderful people Who have worked so hard for this Rail Trail to finally HAPPEN! Congratulations. Many regards, P.K. Ranger…B.V.R.T. Q.L.D.
The progressive opening of these sections of the Northern Rivers Rail Trail will serve to lift the spirits of a community that has collectively suffered such a devastating natural disaster.